Informe PDFConstruction of a water treatment plant and sewer system for the Guaqui town, Department of La Paz / Municipality of Guaqui
Resumen
Información general
Autor
Roberto Méndez
Última actualización
Junio 2018
Objetivo general
Improve the current living conditions of Guaqui´s inhabitants through the implementation of an appropriate sewage system, benefiting the overall population
País
- Bolivia
Presupuesto
Bs. 7'000'000 (approximately USD 1'000'000)
Duración
September 2016 - July 2017 (approximately 10 months)
Resumen
Descripción
Due to the absence of a sewage treatment plant in the Guaqui town, wastewater is discharged directly to Lake Titicaca, causing serious water pollution. Through the construction of a sewage treatment plant, the water pollution will be reduced along with an improvement of the living conditions of the local population. As a result of frequent lake level flucuations, however, the sewage treatment plant might suffer negative impacts from flooding. In addition, frosts during the cold winter months can affect the plant's components such as (i) the sewage collection system and inspection chambers, (ii) emissary, (iii) pumping chamber, (iv) pressure pipe, (v) treatment plant, and (vi) infiltration ditches.
Términos clave
- Wastewater treatment system
- sewage collection system
- emissary
- water pumps
- lake contamination
- Bolivia
- Floods
- frosts
Sectores de Intervención
- Salud
- Turismo
- Agua y saneamiento
Documentos
Perspectiva del riesgo
Amenazas naturales (hidrometeorológicas y geológicas)
Nombre de la amenaza
Crecidas repentinas, inundaciones
Consecuencia
Due to extreme lake level fluctuations, the plant's components could be damaged and filled with sediments. The service would be interrupted. This happens in average every 15 years.
Grado
Sumamente perjudicial
Vulnerabilidades
Disconnected communities, increased pressure on soils and water resources, fragile incomes, relationship between municipality and Risk Management Unit, additional health risks
Probabilidad
Probable
Importancia
Riesgo alto
Riesgo seleccionado
SíMedida seleccionada
SíMedida seleccionada
SíMedida seleccionada
SíMedida seleccionada
SíConsecuencia
Due to flood events, the equipment can not be used and/or broken parts have to be replaced
Grado
Sumamente perjudicial
Vulnerabilidades
Skills: weak technical knowledge, replacement of spare parts, unsufficient access to credits and insurance solutions, lack of ownership of the municipality, emerging local markets and trade
Probabilidad
Probable
Importancia
Riesgo alto
Riesgo seleccionado
SíMedida seleccionada
SíMedida seleccionada
SíConsecuencia
During a flood event, the wastewater could contaminate the river water and cause health problems for the local population. Due to the topography, contaminated water would flow into the lake and not to the urban zone.
Grado
Ligeramente perjudicial
Vulnerabilidades
Health: health education, social hygiene, health stations, health networks, unprotected water sources, precarious health situation
Probabilidad
Probable
Importancia
Riesgo bajo
Nombre de la amenaza
Frío extremo
Consecuencia
Malfunction of the plant and drastic efficiency reduction of the oxidation basins. 90 to 180 days per year with frosts, 3835m a.s.l., average temperatures of 4°C , minimum temperatures -10°C (on average every 2 years)
Grado
Perjudicial
Vulnerabilidades
Operation and efficiency: communities with respiratory infections, lack of maintainance, low technical capacity, frequent interruption of service
Probabilidad
Probable
Importancia
Riesgo medio
Riesgo seleccionado
SíMedida seleccionada
SíPerspectiva del impacto
Impacto negativo en el medioambiente
Componente del proyecto
Water treatment plant (oxidation basins) and pumping chamber
Posible impacto negativo
Bad odors could disturb the surrounding population
Impacto seleccionado
SíMedida seleccionada
SíComponente del proyecto
Location of the water treatment plant
Posible impacto negativo
Landscape changes due to the different construction sites
Impacto seleccionado
SíMedida seleccionada
SíPosible impacto negativo
The system will require large areas for construction
Impacto negativo en los riesgos de desastres
Componente del proyecto
Water treatment plant (oxidation basins)
Posible impacto negativo
New settlements around the plant in the future
Impacto seleccionado
SíMedida seleccionada
SíPosible impacto negativo
Exposure of the Guaqui´s local population to greater risks from natural hazards and increase of vulnerability
Impacto negativo en el cambio climático
Componente del proyecto
Water treatment plant (oxidation basins)
Posible impacto negativo
Greenhouse gas emissions from the oxidation basins
Impacto seleccionado
SíMedida seleccionada
SíPosible impacto negativo
Emission of additional other gases by the water treatment system
Componente del proyecto
Power systems of the plant
Posible impacto negativo
The generators of the different pumping systems run with diesel causing high emissions of GHG and black carbon
Impacto seleccionado
SíMedida seleccionada
Sí